§ 75-61. Inspection.  


Latest version.
  • (a)

    The utility shall make the construction site available to the director and to all others as authorized by law for inspection at all reasonable times during the execution and upon completion of the construction.

    (b)

    At any time, including the time of inspection, the director may order the immediate cessation of any work which poses a serious threat to the health, safety, or welfare of the public, violates any law, or which violates the terms and conditions of the permit and/or this chapter or issue an order to correct work which does not conform to the permit and/or applicable standards, conditions or codes.

    (c)

    When the construction under any permit is completed, the utility shall notify the department.

(Ord. No. 452, § 1, 8-18-09)